DELHI (Metro Rail News): The proposed Delhi Metro Phase V(B) expansion includes eight corridors, with a planned link between Yashobhoomi in Dwarka and Rajiv Chowk in Gurugram. The seven other corridors have received approval from the Delhi government and are awaiting clearance from the Centre, according to an RTI reply accessed by PTI.
The proposed Yashobhoomi Dwarka Sector 25-Rajiv Chowk corridor is among the eight routes submitted to the government for approval. The expansion aims to extend Metro connectivity to several outer areas and densely populated neighbourhoods across Delhi. The seven corridors that have secured the Delhi government’s approval will collectively have 65 stations. Their proposed routes are:
Dhaunsa Bus Stand (Najafgarh)-Nangloi
Central Secretariat-Kishangarh
Samaypur Badli-Narela DDA Sports Complex
Kirti Nagar-Palam
Jor Bagh-Mithapur
Mayur Vihar Phase III-Shastri Park
Keshav Puram-Rohini Sector 34
Delhi Metro Phase V(B): Route details and station network
The proposed corridors vary in length and alignment, with a mix of elevated and underground sections. Their details are as follows:
The 11.9-km Dhaunsa Bus Stand-Nangloi corridor of Delhi Metro will connect areas such as Naresh Park Extension, Ranhola, Bakkarwala, Baprola, Dichaon Kalan and Najafgarh Extension to the Metro network.
The Central Secretariat-Kishangarh route will provide connectivity to New Moti Bagh, RK Puram Sectors 1 and 7, Jawaharlal Nehru University and the Prime Ministers’ Museum. It will also offer interchange facilities at Central Secretariat, Moti Bagh, RK Puram and Kishangarh.
The Samaypur Badli-Narela corridor will extend the existing Yellow Line towards Narela. Similarly, the Kirti Nagar-Palam route will extend the Green Line and improve access for neighbourhoods along the corridor.
The Jor Bagh-Mithapur and Mayur Vihar Phase III-Shastri Park corridors will include substantial underground sections. Meanwhile, the Keshav Puram-Rohini Sector 34 route will extend the network towards Rohini through an entirely elevated alignment.
Delhi Metro Phase V(A): Work progress and completion targets
The RTI reply also provided an update on the earlier Delhi Metro Phase V(A) expansion. Construction is underway on the RK Ashram Marg-Indraprastha corridor, which forms part of the Central Vista Metro link. The Aerocity-IGD Airport Terminal 1 and Tughlakabad-Kalindi Kunj corridors have reached the tendering stage.
Authorities have set September 2029 as the target for completing these three corridors in phases.
Delhi Metro Phase IV: Projects under construction
Work on several Phase IV corridors is also progressing, with completion targets extending up to 2030.
RK Ashram Marg-Janakpuri West: The remaining sections are scheduled for completion by December 2027.
Aerocity-Tughlakabad: Construction is underway, with the same December 2027 deadline.
Lajpat Nagar-Saket G Block: Under construction, with completion targeted for December 2030.
Inderlok-Indraprastha: Work is underway, with a December 2030 target.
Rithala-Kundli: The corridor remains at the tendering stage and is also expected to be completed by December 2030.
The proposed Phase V(B) network would extend Delhi Metro’s reach towards several underserved residential areas and improve links with major transport and activity centres. However, the Yashobhoomi-Rajiv Chowk corridor and the seven other proposed routes remain at different approval stages. Their timelines will become clearer once the Centre takes up the pending proposals.