On September 9, speaking at the opening of a 5.15-km corridor in Goa’s Porvorim, Union Minister of Road Transport and Highways Nitin Gadkari said he was ‘ashamed for the delay that has happened‘ and would skip the inauguration of the highway – expected next year.

The pending stretch in the 472-km Maharashtra section covers five of the 13 packages involved: three km of two bypasses; a 192-metre bridge; another 1.8-km flyover; hill cutting at four locations for 1.5 km; and other ongoing road work, records show.

The Mumbai-Goa highway was first conceived in 2006 as part of the four-lane upgradation of NH-66 as an economic corridor from Panvel near Mumbai to Kanyakumari. Work started in October 2007 on the first 21-km stretch in Maharashtra near the Goa border, which was completed in 2013. Subsequently, most of the other stretches were sanctioned in 2015-16 and contracts awarded in 2017-18.

In December 2016, the Government told Parliament that the highway would be completed by December 2018. This was later revised to 2021, although progress was slow with some of the remaining work being re-awarded, including one as late as October 2025.

On the 120-km Goa section of the NH-66 project, the stretch from the Maharashtra border to Panaji is complete, which means that once work on the pending 8 km on the other side is finished, the highway will link the two state capitals.

Story continues below this ad

The reasons for the continuing delays in Maharashtra range from cash flow issues and loan defaults to issues over land acquisition and local protests, officials and contractors said.

Speaking to the Express, V Umashankar, Secretary, Ministry of Road Transport and Highways (MoRTH), said: “In the last two years, a lot of work was done on stalled stretches and 99% of the highway is through now. All pending work will be completed by April next year.”

So far, the overall cost estimate of the Maharashtra section has ballooned by around 44 per cent, from Rs 12,532 crore to over Rs 18,100 crore. The overrun was primarily because of land acquisition, change of scope in work due to site constraints and construction of additional underpasses following demands from local residents, MoRTH officials said.

A senior official of MoRTH, which is the main implementing agency for the project along with the state PWD, described the situation as ‘a showpiece example of what can go wrong in a major highway project’.

Story continues below this ad

“We have now mandated that the pre-construction activities, like environment and forest clearances, should be complete before inviting the tender. At least 90% of land acquisition should be completed before the project is awarded to contractors,” the official said.

Asked about action taken, the official said, “We are now terminating such contractors. We have also fixed cost limits on the ministry’s projects to state PWDs.”

Mumbai-Goa Highway (NH-66) route map: The 5 pending stretches

What progress reports show: 89% to 98.5%

This newspaper tracked the five delayed packages — and found that the completion rate ranged from 89 per cent to 98.5 per cent. Consider this:

1&2: Panvel to Indapur: 2 sections, 84.6 km, 97.75% complete

Status: Implemented by NHAI. Contract awarded in 2011, completion deadline 2020, re-awarded 2022-23.

Delay: Cash flow issues, loan default, land acquisition.

Story continues below this ad

Contractors: Consortium including Supreme Infrastructure, which was on RBI’s top-100 bank defaulters list in 2019; contract terminated, balance work re-awarded to firm owned by J M Mhatre, a businessman under probe by Enforcement Directorate (ED).

Bottom line: Original cost Rs 943 crore, cost settlement currently in arbitration.

Two packages, Panvel to Kasu and Kasu to Indapur, were awarded to a consortium led by Supreme Infrastructure India, a listed company. The consortium included its subsidiary Supreme Infrastructure BOT Pvt Ltd (64 per cent share together), City Universe Ltd, a subsidiary of China State Construction Engineering (Hong Kong) Ltd, and Mahavir Roads and Infrastructure.

The entire 84-km section was first awarded as a BOT (Build-Operate-Transfer) project and the contractors completed 36 km by 2017. Subsequently, Supreme Infrastructure defaulted on bank loans and figured among RBI’s top-100 bank defaulters in 2019.

Story continues below this ad

Under a restructuring plan backed by the National Company Law Tribunal (NCLT) in March 2025, the debt fell from Rs 2,200 crore to Rs 464 crore. Supreme Infrastructure BOT Pvt Ltd later went into liquidation. The consortium’s contract was terminated in 2021.

Panvel to Kasu: Awarded to J M Mhatre Infra Pvt Ltd in March 2023. The Panvel-based firm belongs to politician and businessman J M Mhatre, who is under ED investigation for alleged fraud involving forest land. Mhatre, who was associated with Peasants and Workers Party, joined BJP in 2025. He holds over 17 per cent share in the company, with the remainder held by family members. The company reported profits of Rs 5.08 crore in FY 2024-25.

Kasu to Indapur: Awarded in November 2022 to Kalyan Toll Infrastructure Ltd, an Indore-based company belonging to the Kalyan group. The company reported a profit of Rs 141 crore in FY 2024-25.

Mhatre, his company and Kalyan Toll did not respond to emails and calls from The Indian Express. Officials said land acquisition and utility shifting issues were resolved but Supreme Infra faced financial issues.

Story continues below this ad

3. Indapur to Wadpale: 26.75 km, 89% complete

Status: Implemented by MoRTH. Contract awarded in December 2017, completion deadline 2021, contractors terminated; balance work re-awarded in October 2025.

Delay: Forest clearances, shifting of utilities, land acquisition and pre-construction activities.

Contractors: Joint venture of Chetak Enterprises and APCO Infratech. Chetak is owned by Udai Lal Anjana, a Congress leader and former Rajasthan minister of co-operatives between 2018 and 2023. Contract terminated in 2025, remaining work awarded to Jaipur-based LNA Infraprojects.

Bottom line: Cost escalated from Rs 1,203 crore to Rs 1,657 crore.

Story continues below this ad

The section was awarded in 2017 to a joint venture of Udaipur-based Chetak Enterprises and APCO Infratech. Records filed with the Registrar of Companies (ROC) show that Congress leader Udai Lal

Anjana holds over 40 per cent share in Chetak Enterprises, and close to 87 per cent with his family members. The company made a profit of Rs 32.46 crore in FY25. Lucknow-based APCO Infratech is run by Anil Kumar Singh, an industrialist from UP, who holds over 37 per cent stake. The company made a profit of Rs 738 crore in FY25.

Due to multiple delays, the ministry terminated the contractors in June 2025. The balance work of 10.6 km for the Indapur and Mangaon bypasses was awarded in October 2025 to Jaipur-based LNA Infraprojects. The work is scheduled to be completed by March 2027.

Udai Lal Anjana could not be reached for comment. His brother Manohar Lal Anjana, who holds 26.66 per cent stake in the company, said, “I know that we have two sections in the project but I am not aware of its status.” APCO Infratech did not respond to an emailed request for comment.

Story continues below this ad

4: Parashuram Ghat to Arawali: 34.45 km, 98.50% complete

Status: Implemented by MoRTH. Contract awarded in December 2017, completion deadline 2021, 1.8-km Chiplun flyover pending.

Contractors: Joint venture of Chetak Enterprises, owned by Congress leader Udai Lal Anjana, and Eagle Infra India Ltd.

Delay: Land acquisition, court cases.

Bottom line: Cost has escalated from Rs 983 crore to Rs 2,226 crore.

Chetak Enterprises, whose services were terminated in the Indapur-Wadpale section for delays, was awarded a second section in a joint venture with Thane-based Eagle Infra India Ltd in December 2017. That, too, is yet to be completed.

Eagle Infra India, a major road contractor in Maharashtra, is run by the Rupchandani family, with Udhav Rupchandani serving as CEO and managing director of the company. The Rs 929-crore company registered a profit of Rs 253 crore in FY25.

The section is scheduled to be opened for commercial operation in November 2026, with the completion of the 1.8-km flyover in Chiplun. Eagle Infra did not respond to an emailed request from The Indian Express for comment.

5. Arawali to Kante: 39.24 km, 95% complete

Status: Implemented by MoRTH. Contract awarded in November 2017, completion deadline 2021; original contractor in insolvency, work re-awarded in 2024.

Delay: Local demands of high compensation and protests, cash flow, loan default.

Contractors: Hazoor Infra Projects Pvt Ltd, a subsidiary of Hazoor Multi Projects Ltd, a listed company. The chairman and managing director of Hazoor Multi Projects, Radheshyam Mopalwar, is a former vice chairman and MD of Maharashtra State Road Development Corporation, who helmed the Samruddhi Mahamarg Expressway project.

Bottom line: Cost rose from Rs 1,102 crore to Rs 1,443 crore.

The other delayed section, Arawali to Kante, was awarded in 2017 to a joint venture of MEP Infrastructures Developers Ltd and San Jose India Infrastructure & Constructions Pvt Ltd. Incorporated in 2002, MEP is a listed company with majority share held by Mumbai’s Mhaiskar family and Jayant D Mhaiskar as its chairman and managing director. San Jose India is a subsidiary of a Spanish group.

The work was delayed and MEP defaulted on a loan of Rs 128 crore from Intec Capital Ltd. Following this, the NCLT initiated the Corporate Insolvency Resolution Process (CIRP) against MEP in March 2024. This necessitated the ministry re-inviting the tender for both sections. The project was awarded in 2024 to Hazoor Infra Projects Pvt Ltd. ROC records show Hazoor Infra, incorporated in October 2023 as a special purpose vehicle (SPV) for the NH-66 section, registered a profit of around Rs 12 crore in FY25.

Work on the Sangameshwar bridge approach and hill cutting at four locations (Kurdhunda, Kolambe, Wandri and Kante, 1.5 km) is yet to be completed in this section.

A top executive of Hazoor Infra said, “The remaining section will be done in a month. Since the section passes through populated areas, there was a problem in blasting and there were acquisition problems regarding a Railway section, a temple and a crematorium.”

Jayant Mhaiskar, chairman and managing director of MEP Infrastructure Developers, said, “Since the project has not been with us for the last five years, we would not be able to comment. The company is still under CIRP.”